Financial highlights
Revenue
(2023: €1,922m)
Cash generated from operations
(2023: €1,049m)
EBITDA
(2023: €887m)
Capital expenditure
(2023: €282m)
Net income
(2023: €270m)
Net cash
(2023: €1032m)
Reduced our water use by 10.5% compared to our baseline year of 2020
53% reduction in carbon emissions (scope 1 and 2) from our baseline year of 2019
Enriched enough uranium to generate an estimated 740,000 GWh of electricity from nuclear power, avoiding approximately 390 million tonnes of carbon emissions
Invested over €6.5 million in our social impact programme since 2021
Bulgaria
In March, Bulgaria’s Parliament ratified the intergovernmental agreement with the US on the construction of two nuclear reactors, at Kozloduy-7 and -8, which will use Westinghouse AP1000 technology.
Czech Republic
Like many countries, the Czech Republic is seeking to become more energy independent and reduce its reliance on fossil fuels. In July, South Korea’s KHNP won the Czech Government's competition for up to four new nuclear power units in the country. In September, the Czech Republic also chose UK’s Rolls-Royce SMR for a proposed SMR programme following an assessment of seven potential technology suppliers. The first SMR is planned by ČEZ at a site near the existing Temelín nuclear power plant in the 2030s.
France
In July, EDF announced that it would provide details of a plan for eight new reactors by the end of 2026, following a final investment decision on six reactors already in the planning stage. However, highlighting the ongoing challenges of constructing new nuclear facilities, the Government reported in March that the first commissioning of one of those six EPR2 reactors is now scheduled for 2038, delayed from the previously planned 2035.
Germany
Following the final s tage of its nuclear phase out policy in 2023, which saw all units shut down, the country continued its decommissioning and dismantling of power plants.
Netherlands
In October 2025, the Dutch Government formally submitted an amendment to the Nuclear Energy Act to Parliament that would allow the Borssele nuclear power plant to operate well beyond its current planned closure in 2033 – potentially until 2054 if safety conditions are met.
Meanwhile, Dutch authorities have also expanded potential sites for two nuclear reactors and potentially two additional reactors. These include locations such as Tweede Maasvlakte (Rotterdam) and Terneuzen. However, because of this additional required work, the Government acknowledged that the earlier 2035 target for bringing the first new large reactor into operation will be difficult to meet. The new Dutch government took office on February 23 and will continue the nuclear programme.
Poland
In December, the European Commission concluded that Poland’s planned public support for its first largescale nuclear power plant complies with EU state aid rules, paving the way for the Government to sign a construction contract with a consortium of American companies led by Westinghouse. Poland aims to begin construction of the first unit of the plant in 2028 and complete it in 2036.
Complementing this flagship project, Poland is also moving into SMRs. In August, it selected Włocławek as the site for its first SMR installation, where it plans to deploy two 300MW GE Hitachi BWRX-300 units by 2035, underscoring the country’s dual strategy of combining traditional nuclear capacity with emerging modular technologies.
Romania
Fluor Corporation, majority investor in Oregon-based SMR developer NuScale, and RoPower have signed an agreement that will enable Romania’s SMR project to move to a final investment decision and construction, with deployment targeted for 2029.
Slovak Republic
Slovakia has approved an agreement with the United States to build an additional nuclear reactor at the existing site in Jaslovské Bohunice. The planned reactor will have an output of over 1GW and be fully owned by the state.
Sweden
In May, Sweden's parliament passed legislation to finance a new generation of nuclear reactors that the Government views as essential for energy security and achieving net zero emissions by 2045. The plan envisions four large scale reactors - totalling around 5GW of capacity - or an equivalent amount delivered through SMRs, with half of the new capacity targeted to be online by 2035.
Complementing the Government’s wider push for new nuclear capacity, Vattenfall reported in August that it had decided to pursue SMRs for its next phase of development. The company aims to deploy new capacity on the Värö Peninsula, home to the Ringhals nuclear power plant, in the early 2030s. The project is planned for 1.5GW of capacity.
Later in the year, Sweden reinforced this broader nuclear strategy by addressing fuel-supply constraints. In November, parliament lifted the country’s long standing ban on uranium mining as part of its effort to support new reactor construction.
Switzerland
In August, the Swiss Government reported that it would seek to lift the country's ban on the construction of new nuclear power plants, which has been in place since 2018. It said all clean energy sources will be needed to meet future electricity demand.
UK
In February, the UK Government announced plans to expand nuclear power, pledging to open additional sites nationwide for new power stations. This builds on the Government’s push for technology companies to collaborate on developing SMRs capable of powering energy-intensive AI datacentres across Britain. As part of this wider expansion plan, the Government will, for the first time, allow nuclear projects to be developed outside the eight previously designated sites. Complementing this shift, forthcoming planning reforms are intended to speed up the rollout of SMRs.
In June, Great British Energy-Nuclear, the public-sector body responsible for supporting new nuclear projects under the UK’s clean energy plans, selected Rolls- Royce SMR as the preferred bidder to build the UK’s first SMR. The programme aims to reach a final investment decision in 2029, with initial units expected online in the mid- 2030s. The Government confirmed Wylfa in North Wales as the chosen site, where three Rolls-Royce SMR units are planned. Early works are expected to begin around 2026.
In July, the UK signed the final investment decision for the Sizewell C nuclear power plant and became the largest shareholder in the £38 billion project alongside EDF, Centrica, La Caisse and Amber Infrastructure.
In September, X-Energy and Centrica announced plans to build up to 12 advanced modular reactors in Hartlepool, with a follow-on UK wide programme targeting a fleet of 6GW of nuclear power. According to the companies, the Hartlepool project would generate enough power for up to 1.5 million homes and create up to 2,500 jobs.
However, a government review published in November highlighted significant challenges for nuclear new build in the UK . The Prime Minister has accepted the principle of the report’s recommendations , including a new Commission for Nuclear Regulation.
USA
Strong bipartisan support sustained the USA’s rapid nuclear momentum in 2025, spanning fleet extensions, restarts of shuttered units, and announcements of new projects, including both large reactors and advanced designs.
In May, President Trump signed four executive orders aimed at quadrupling US nuclear capacity by 2050, accelerating reactor approvals, strengthening domestic uranium production and enrichment, and boosting deployment of advanced nuclear technologies. The orders direct the DOE to support the start of construction on ten large reactors by 2030, finance power uprates across the existing fleet, and implement a “wholesale revision” of NRC rules and guidelines.
Following the executive orders, Westinghouse announced plans to build ten large reactors in the US, targeting construction by 2030. Later in the year, Westinghouse’s owners, Cameco and Brookfield Asset Management, announced a strategic partnership with the federal Government, aligned with the executive orders, targeting at least $80 billion of new reactors.
NextEra Energy plans to restart the Duane Arnold Energy Centre in Iowa, with full operation targeted by Q1 2029, supported by a Google power purchase agreement to supply cloud and AI operations. The plant originally shut down in 2020 after it was deemed no longer economically viable under market conditions at the time.
Constellation reports that its project to restart Three Mile Island-1 in Pennsylvania, renamed the Crane Clean Energy Center (CCEC), remains ahead of schedule, with the unit expected back online in 2027. The plant was approved for restart in 2024 and is underpinned by a 20-year agreement with Microsoft to power its data centres.
Technology companies continue to drive strong demand for nuclear energy. In June, Meta signed a 20-year contract to purchase output from Constellation’s Clinton nuclear plant starting mid-2027, securing the plant’s long-term future. In the same month, Talen Energy entered a power purchase agreement through 2042 for 1.92GW of carbon-free electricity to support Amazon’s AI and cloud operations, while exploring SMR options.
New build and expansion projects elsewhere are also progressing. In October, Brookfield signed a letter of intent with Santee Cooper to explore purchasing and completing the two unfinished AP1000 reactors at V.C. Summer which advanced to a formal MOU for a feasibility study with a target final investment decision by June 2026. If completed, the units could generate more than 2GW of carbon-free power.
Meanwhile, the New York Power Authority issued its first call for proposals to develop advanced nuclear reactors in upstate communities, aiming to add at least 1GW of capacity by 2040. In November, Constellation proposed a range of measures for the Calvert Cliffs Clean Energy Center, including 20 year life extensions for its two existing units.
The US Government itself moved quickly in 2025 to accelerate the development of advanced reactors. In May, Kairos Power completed the first installation of nuclear safety-related concrete for the Hermes Low-Power Demonstration Reactor in Oak Ridge, Tennessee, the first advanced reactor to receive an NRC construction permit, marking the start of “nuclear construction.” In July, the DOE was mandated to authorise and develop three pilot SMRs to meet surging AI demand, aiming for “criticality” by July 2026, while the Department of Defense was directed to commission its own pilot reactor within three years. At the same time, the NRC completed its environmental review and safety evaluation of TerraPower’s Natrium reactor outside Kemmerer. The plant is still projected to come online around 2030.
In November, Valar Atomics achieved criticality, becoming the first nuclear startup to create a critical fission reaction under the DOE pilot program established following the May executive orders.
China
In April, the Chinese Government approved another ten nuclear reactors across five sites – this takes total approvals to 41 units in the last four years. Meanwhile, Zhangzhou-1, the first unit at Zhangzhou Nuclear Power Plant began commercial operation in January 2025. Zhangzhou-2 is expected to enter commercial operation soon.
Japan
In July, nuclear operator Kansai Electric Power Company announced it will begin surveys for a new reactor at its Mihama power station in Fukui prefecture, Western Japan, intended to replace the existing facility. This marks Japan’s first concrete step toward building a new nuclear reactor since 2011. Kansai Electric had been studying a successor to the Mihama-1 reactor since November 2010 but suspended the project after 2011.
This announcement follows the Government’s February revision of its Basic Energy Plan, which now allows electric power companies that have decommissioned nuclear plants to construct new reactors on the sites of other existing nuclear facilities under a “reconstruction” framework.
Meanwhile, restarts of Japan’s existing fleet are progressing steadily. Shimane-2 returned to commercial operation in January, while Kashiwazaki Kariwa-6 and Tomari-3 have received restart approvals and are targeting returns to service in 2026 and 2027, respectively.
South Korea
In February, South Korea cancelled one of three planned large reactors following the impeachment of pro-nuclear former president Yoon Suk Yeol. His removal shifted political influence toward the renewables-oriented opposition, prompting a reduction in the country’s nuclear expansion plans: the target for new nuclear capacity by 2038 was cut from 4.9 GW to 3.5 GW. Even so, the Government continues to pursue new technologies, including SMR projects with total capacity of around 700 MW, aiming for completion by
2036.
Progress on existing projects has continued as well. In May, KHNP announced the pouring of first concrete for Shin Hanul-3, with completion expected in 2032. Another significant development came in November, when the Nuclear Safety and Security Commission approved a 10-year life extension for Kori-2, the country’s oldest operating reactor. Kori-2 had been shut down in April 2023 after reaching the end of its original 40-year design life, and the extension will allow it to operate until April 2033. This marks a major policy shift, potentially opening the door to similar extensions for up to nine other ageing reactors as concerns grow about future power supply shortages amid rising electricity demand.
UAE
The UAE will reportedly tender for the construction of four new reactors, with the aim to have them operational by 2032 in order to meet projected energy needs. Meanwhile, the fourth and final unit at the Barakah nuclear power plant began commercial operation in September, marking the full delivery of a project that will generate 25% of the UAE’s electricity needs.
-
Bulgaria
In March, Bulgaria’s Parliament ratified the intergovernmental agreement with the US on the construction of two nuclear reactors, at Kozloduy-7 and -8, which will use Westinghouse AP1000 technology.
-
Czech Republic
Like many countries, the Czech Republic is seeking to become more energy independent and reduce its reliance on fossil fuels. In July, South Korea’s KHNP won the Czech Government's competition for up to four new nuclear power units in the country. In September, the Czech Republic also chose UK’s Rolls-Royce SMR for a proposed SMR programme following an assessment of seven potential technology suppliers. The first SMR is planned by ČEZ at a site near the existing Temelín nuclear power plant in the 2030s.
-
France
In July, EDF announced that it would provide details of a plan for eight new reactors by the end of 2026, following a final investment decision on six reactors already in the planning stage. However, highlighting the ongoing challenges of constructing new nuclear facilities, the Government reported in March that the first commissioning of one of those six EPR2 reactors is now scheduled for 2038, delayed from the previously planned 2035.
-
Germany
Following the final s tage of its nuclear phase out policy in 2023, which saw all units shut down, the country continued its decommissioning and dismantling of power plants.
-
Netherlands
In October 2025, the Dutch Government formally submitted an amendment to the Nuclear Energy Act to Parliament that would allow the Borssele nuclear power plant to operate well beyond its current planned closure in 2033 – potentially until 2054 if safety conditions are met.
Meanwhile, Dutch authorities have also expanded potential sites for two nuclear reactors and potentially two additional reactors. These include locations such as Tweede Maasvlakte (Rotterdam) and Terneuzen. However, because of this additional required work, the Government acknowledged that the earlier 2035 target for bringing the first new large reactor into operation will be difficult to meet. The new Dutch government took office on February 23 and will continue the nuclear programme. -
Poland
In December, the European Commission concluded that Poland’s planned public support for its first largescale nuclear power plant complies with EU state aid rules, paving the way for the Government to sign a construction contract with a consortium of American companies led by Westinghouse. Poland aims to begin construction of the first unit of the plant in 2028 and complete it in 2036.
Complementing this flagship project, Poland is also moving into SMRs. In August, it selected Włocławek as the site for its first SMR installation, where it plans to deploy two 300MW GE Hitachi BWRX-300 units by 2035, underscoring the country’s dual strategy of combining traditional nuclear capacity with emerging modular technologies.
-
Romania
Fluor Corporation, majority investor in Oregon-based SMR developer NuScale, and RoPower have signed an agreement that will enable Romania’s SMR project to move to a final investment decision and construction, with deployment targeted for 2029.
-
Slovak Republic
Slovakia has approved an agreement with the United States to build an additional nuclear reactor at the existing site in Jaslovské Bohunice. The planned reactor will have an output of over 1GW and be fully owned by the state.
-
Sweden
In May, Sweden's parliament passed legislation to finance a new generation of nuclear reactors that the Government views as essential for energy security and achieving net zero emissions by 2045. The plan envisions four large scale reactors - totalling around 5GW of capacity - or an equivalent amount delivered through SMRs, with half of the new capacity targeted to be online by 2035.
Complementing the Government’s wider push for new nuclear capacity, Vattenfall reported in August that it had decided to pursue SMRs for its next phase of development. The company aims to deploy new capacity on the Värö Peninsula, home to the Ringhals nuclear power plant, in the early 2030s. The project is planned for 1.5GW of capacity.
Later in the year, Sweden reinforced this broader nuclear strategy by addressing fuel-supply constraints. In November, parliament lifted the country’s long standing ban on uranium mining as part of its effort to support new reactor construction.
-
Switzerland
In August, the Swiss Government reported that it would seek to lift the country's ban on the construction of new nuclear power plants, which has been in place since 2018. It said all clean energy sources will be needed to meet future electricity demand.
-
UK
In February, the UK Government announced plans to expand nuclear power, pledging to open additional sites nationwide for new power stations. This builds on the Government’s push for technology companies to collaborate on developing SMRs capable of powering energy-intensive AI datacentres across Britain. As part of this wider expansion plan, the Government will, for the first time, allow nuclear projects to be developed outside the eight previously designated sites. Complementing this shift, forthcoming planning reforms are intended to speed up the rollout of SMRs.
In June, Great British Energy-Nuclear, the public-sector body responsible for supporting new nuclear projects under the UK’s clean energy plans, selected Rolls- Royce SMR as the preferred bidder to build the UK’s first SMR. The programme aims to reach a final investment decision in 2029, with initial units expected online in the mid- 2030s. The Government confirmed Wylfa in North Wales as the chosen site, where three Rolls-Royce SMR units are planned. Early works are expected to begin around 2026.
In July, the UK signed the final investment decision for the Sizewell C nuclear power plant and became the largest shareholder in the £38 billion project alongside EDF, Centrica, La Caisse and Amber Infrastructure.
In September, X-Energy and Centrica announced plans to build up to 12 advanced modular reactors in Hartlepool, with a follow-on UK wide programme targeting a fleet of 6GW of nuclear power. According to the companies, the Hartlepool project would generate enough power for up to 1.5 million homes and create up to 2,500 jobs.
However, a government review published in November highlighted significant challenges for nuclear new build in the UK . The Prime Minister has accepted the principle of the report’s recommendations , including a new Commission for Nuclear Regulation.
-
USA
Strong bipartisan support sustained the USA’s rapid nuclear momentum in 2025, spanning fleet extensions, restarts of shuttered units, and announcements of new projects, including both large reactors and advanced designs.
In May, President Trump signed four executive orders aimed at quadrupling US nuclear capacity by 2050, accelerating reactor approvals, strengthening domestic uranium production and enrichment, and boosting deployment of advanced nuclear technologies. The orders direct the DOE to support the start of construction on ten large reactors by 2030, finance power uprates across the existing fleet, and implement a “wholesale revision” of NRC rules and guidelines.
Following the executive orders, Westinghouse announced plans to build ten large reactors in the US, targeting construction by 2030. Later in the year, Westinghouse’s owners, Cameco and Brookfield Asset Management, announced a strategic partnership with the federal Government, aligned with the executive orders, targeting at least $80 billion of new reactors.
NextEra Energy plans to restart the Duane Arnold Energy Centre in Iowa, with full operation targeted by Q1 2029, supported by a Google power purchase agreement to supply cloud and AI operations. The plant originally shut down in 2020 after it was deemed no longer economically viable under market conditions at the time.
Constellation reports that its project to restart Three Mile Island-1 in Pennsylvania, renamed the Crane Clean Energy Center (CCEC), remains ahead of schedule, with the unit expected back online in 2027. The plant was approved for restart in 2024 and is underpinned by a 20-year agreement with Microsoft to power its data centres.
Technology companies continue to drive strong demand for nuclear energy. In June, Meta signed a 20-year contract to purchase output from Constellation’s Clinton nuclear plant starting mid-2027, securing the plant’s long-term future. In the same month, Talen Energy entered a power purchase agreement through 2042 for 1.92GW of carbon-free electricity to support Amazon’s AI and cloud operations, while exploring SMR options.
New build and expansion projects elsewhere are also progressing. In October, Brookfield signed a letter of intent with Santee Cooper to explore purchasing and completing the two unfinished AP1000 reactors at V.C. Summer which advanced to a formal MOU for a feasibility study with a target final investment decision by June 2026. If completed, the units could generate more than 2GW of carbon-free power.
Meanwhile, the New York Power Authority issued its first call for proposals to develop advanced nuclear reactors in upstate communities, aiming to add at least 1GW of capacity by 2040. In November, Constellation proposed a range of measures for the Calvert Cliffs Clean Energy Center, including 20 year life extensions for its two existing units.
The US Government itself moved quickly in 2025 to accelerate the development of advanced reactors. In May, Kairos Power completed the first installation of nuclear safety-related concrete for the Hermes Low-Power Demonstration Reactor in Oak Ridge, Tennessee, the first advanced reactor to receive an NRC construction permit, marking the start of “nuclear construction.” In July, the DOE was mandated to authorise and develop three pilot SMRs to meet surging AI demand, aiming for “criticality” by July 2026, while the Department of Defense was directed to commission its own pilot reactor within three years. At the same time, the NRC completed its environmental review and safety evaluation of TerraPower’s Natrium reactor outside Kemmerer. The plant is still projected to come online around 2030.
In November, Valar Atomics achieved criticality, becoming the first nuclear startup to create a critical fission reaction under the DOE pilot program established following the May executive orders.
-
China
In April, the Chinese Government approved another ten nuclear reactors across five sites – this takes total approvals to 41 units in the last four years. Meanwhile, Zhangzhou-1, the first unit at Zhangzhou Nuclear Power Plant began commercial operation in January 2025. Zhangzhou-2 is expected to enter commercial operation soon.
-
Japan
In July, nuclear operator Kansai Electric Power Company announced it will begin surveys for a new reactor at its Mihama power station in Fukui prefecture, Western Japan, intended to replace the existing facility. This marks Japan’s first concrete step toward building a new nuclear reactor since 2011. Kansai Electric had been studying a successor to the Mihama-1 reactor since November 2010 but suspended the project after 2011.
This announcement follows the Government’s February revision of its Basic Energy Plan, which now allows electric power companies that have decommissioned nuclear plants to construct new reactors on the sites of other existing nuclear facilities under a “reconstruction” framework.
Meanwhile, restarts of Japan’s existing fleet are progressing steadily. Shimane-2 returned to commercial operation in January, while Kashiwazaki Kariwa-6 and Tomari-3 have received restart approvals and are targeting returns to service in 2026 and 2027, respectively.
-
South Korea
In February, South Korea cancelled one of three planned large reactors following the impeachment of pro-nuclear former president Yoon Suk Yeol. His removal shifted political influence toward the renewables-oriented opposition, prompting a reduction in the country’s nuclear expansion plans: the target for new nuclear capacity by 2038 was cut from 4.9 GW to 3.5 GW. Even so, the Government continues to pursue new technologies, including SMR projects with total capacity of around 700 MW, aiming for completion by
2036.Progress on existing projects has continued as well. In May, KHNP announced the pouring of first concrete for Shin Hanul-3, with completion expected in 2032. Another significant development came in November, when the Nuclear Safety and Security Commission approved a 10-year life extension for Kori-2, the country’s oldest operating reactor. Kori-2 had been shut down in April 2023 after reaching the end of its original 40-year design life, and the extension will allow it to operate until April 2033. This marks a major policy shift, potentially opening the door to similar extensions for up to nine other ageing reactors as concerns grow about future power supply shortages amid rising electricity demand.
-
UAE
The UAE will reportedly tender for the construction of four new reactors, with the aim to have them operational by 2032 in order to meet projected energy needs. Meanwhile, the fourth and final unit at the Barakah nuclear power plant began commercial operation in September, marking the full delivery of a project that will generate 25% of the UAE’s electricity needs.
- Over 2,550 highly skilled and well-trained employees, supported through employee engagement initiatives
- Leading centrifuge technology
- Safe, well-maintained operations
- Reliable transatlantic transportation services
- Research & Development (R&D) programmes
- Strong customer service
- Rigorous supplier and compliance audits
- Advanced market intelligence
- Robust commitment to nuclear safeguards and non-proliferation through the Treaties of Almelo,
- Washington and Cardiff and government oversight
- Integrated and diverse nuclear fuel supply to deliver energy security
- Progression of the capacity programme to ensure that demand is matched by supply for customers
worldwide - Evolution of the nuclear fuel cycle through the development of advanced fuels for next-generation
reactors, including LEU+ (low enriched uranium up to 10%) and HALEU (high-assay low-enriched
uranium up to 19.75%) - Commitment to reduce our emissions from our direct operations (scopes 1 and 2) by 90% and our supply
chain (scope 3) by 30% by 2030, with the goal of being a sustainable, net zero business by 2040 - Enhanced isotopes offering for medical, industrial and research applications
- Responsible nuclear stewardship, including materials management and decommissioning
- Revenue: €1,877 million (2023: €1,922 million)
- EBITDA(i): €728 million (2023: €887 million)
- Net income: €180 million (2023: €270 million)
- Cash generated from operations: €668 million (2023: €1,049 million)
- Capital expenditure(ii): €471 million (2023: €282.0 million)
- Net cash: €893 million (2023: €1,032 million)
- Contract order book extending into the 2040s; its value as of 31 December 2024 grew to €18.7 billion
(2023: €14.7 billion) - Investment grade credit ratings: S&P Global: A- (stable outlook); Moody’s: Baa1 (stable outlook)
(i) EBITDA is earnings before exceptional items, interest (including other finance costs), taxation, depreciation and amortisation and results from joint venture and other investments. Depreciation and amortisation are adjusted to remove elements of such charges included in changes to inventories and net costs of nuclear provisions. Further details on the calculation of EBITDA are set out in note 4 to the Group’s Consolidated Financial Statements contained in the Annual Report and Accounts.
(ii) Capital expenditure includes net cash flows on the purchases of property, plant and equipment and intangible assets of €462.7 million (2023: €278.4 million) and on the decrease of capital accruals of €8.7 million (2023: €3.9 million) (included in working capital payables).
- Global enrichment capacity of 17.3 million tSW/a (2023: 17.6 million)
- Enriched enough uranium to generate an estimated 740,000 GWh of electricity from nuclear power,
avoiding approximately 390 million tonnes of carbon emissions - Our uranium enrichment services provided:
enough fuel to generate the power supply for more than 90% of all the households in the EU and UK for one
year or more than 50% of all the households in the US for one year - More than 50 customers in 20 countries
- 100% of customer deliveries met
- Volume of annual isotopes’ sales equates to more than two million patient treatments being performed
using medical radioisotopes produced from our products - Total Recordable Injury Rate (TRIR) of 0.291 as a result of 10 total recordable injuries (2023: TRIR 0.248)
- Carbon emissions decreased by 33% (scopes 1 and 2 – direct and indirect emissions) from 2023, and fell
by 53% from 2019 baseline year - Water withdrawal increased slightly compared to 2023, but remains below the baseline year of 2020 by 10.5%
- Reduced our total energy use by 3% compared to 2023
- New charitable/social impact partnerships established, supporting educational goals
- Global ‘Richie’ STEM education programme has reached around 55,000 children in 2024




April 2024
April 2024
May 2024
May 2024
June 2024
June 2024
July 2024
July 2024
August 2024
August 2024
September 2024
September 2024
October 2024
October 2024
October 2024
October 2024
December 2024
December 2024
December 2024
December 2024